Green Capital completes conceptual engineering phase for planned data center in Chubut

Jorge Vilariño, the Polish company’s representative in Argentina, spoke to Convergencialatina about the current status of its data center projects in Chubut and Santa Cruz. The more advanced project is located in Trelew, along Route 3, where the conceptual engineering phase has been completed, including estimates of the required power capacity and other technical details. Environmental impact studies are now underway for this project, as well as for the planned data center in Santa Cruz province, about 100 kilometers north of Río Gallegos.